ComEd Project: Peterson Ave. & Central Park Ave.

ComEd Project – Peterson Ave. & Central Park Ave. Conduit and Manhole Installation

ComEd is making system improvements in order to provide more reliable service to their customers. During this project, ComEd will be installing a new feeder to provide increased reliability and capacity to the area.

Vehicles require access at critical locations, and at times will be blocking street parking, alleys and traffic lanes. The manner and duration of blockings will be determined by the needs of the project at any given location.

The following is a time frame for the completion of the project:

  • Peterson Ave. & Central Park Ave: Installation of new conduit - Start date of 6/7/17; complete date of 6/13/17
  • Peterson Ave. & Lawndale Ave: Manhole removal and rebuild - Start date of 6/14/17; complete date of 7/7/17
  • Lawndale Ave. from Peterson Ave. to the alley north: Start date of 6/14/17; complete date of 6/23/17

Updates for ComEd Project: Peterson Ave. & Central Park Ave.