Navajo Gas Project - Fall 2016

39th Ward Gas Project - Fall 2016
PROJECT DESCRIPTION

Project Description: A Peoples Gas project will begin the week of October 17, 2016, at 6200 N Navajo. This project will involve some work on Devon and Caldwell as well. Crews will be installing 3,000 feet of new main and transfer 42 services. Construction will begin on Navajo, then move to Devon and Caldwell. (See map of work below.)
 
Reason: The goal of the project is to resolve a poor supply issue on this block.

Timing: This project starts the week of October 17, 2016, and should take about 8 weeks and end mid-to-late December 2016.

Traffic: Expect traffic delays on Navajo, Caldwell, and Devon. (See map below.)

Parking: "No Parking” signs will be posted as needed. Please heed posted signs.

 

Updates for Navajo Gas Project - Fall 2016